RC residence, 40 tsubo — 17-month model

StageDuration
Schematic design2.5 months
Detailed design3 months
Permit + structural review1.5 months
Contractor selection1 month
Ground improvement + foundation1.5 months
Frame (concrete + curing)3 months
Envelope, waterproofing, roof1.5 months
Fit-out and services2.5 months
Inspection and handover0.5 month

Wood residence, 35 tsubo — 9-month model

Schematic + detailed design3–4 months
Permit1 month
Ground + foundation1 month
Framing + roof0.5 month
Fit-out and services2.5 months
Inspection and handover0.5 month

Three forces that shape the calendar

1. Concrete curing

RC frames need minimum 3 days before formwork can be stripped, and 28 days to design strength. Rushing the strip causes cracking and weakens the shell.

2. Rainy season and typhoons

June–July (tsuyu) and August–October (typhoons) halt exterior works. Targeting foundation pours for spring or autumn dramatically tightens the calendar.

3. Permit congestion

Osaka and Tokyo review bodies bunch up in April and October — expect roughly two weeks of slippage. Pre-consultation with the architect mitigates this.

Compared with Western practice, Japanese timelines look long. The reason is permit rigour and the curing / drying time demanded by the humid climate. Length here buys precision, not slack.